This guide explains how make one-time purchase requests, including supplies that are listed or not listed in BearBUY punchout catalogs (Office Max, Grainger, Apple, etc.), OR invoice payment requests.

Step 1: Staff

Gather Order Details 

  • Complete the One-Time Purchase Request Form
    • If you are requesting purchases from two different vendors, submit two separate requests to our team
    • Receive approval from your supervisor. Approvals should include:
      • Detailed business purpose that clearly explains how the expense supports the program and/or University's mission
      • Chartstring & Expense Total Amount
      • Wet or Digital Approval Signature (Email approvals are no longer accepted).
    • For Invoice Payment Requests, upload an invoice

Step 2: Admin 

Review and Process Purchase Request

  • Once your request have been received by the Admin team, it will be moved to our queue to be processed within 3-5 business days

  • Once your request has been reviewed and processed in BearBUY, staff will receive a email confirmation that the requested was processed and submitted. 

Step 3: BearBUY 

BearBUY Workflows

  • Requisition Creator receives, reviews, and processes the request to initiate purchasing

  • Org Node Approver (Financial Analyst) reviews and approves the request

  • A Purchase Order (PO) is created and purchasing will begin 

Step 4: Staff

Supplies Delivery OR Invoice Payment Processing

  • Supplies/Goods Delivery:

    • Receive items from vendor (delivery or pick-up)

    •  Notify the Admin Team upon receiving items

  • Invoice Payment Request:

    • The invoice will be processed and paid.

Step 5: Admin 

Mark the Request Complete

  • Supplies Requests:

    • Once the Admin Team receives confirmation from Staff of delivery of goods, the Admin Team will mark the Request complete
    • Staff will receive a confirmation email, and the request will be marked as "completed."
  • Invoice Payment Requests:

    • Staff will receive a confirmation email, and the request will be marked as "completed."
Expected Processing Timeframes by Role
RoleTimelineNotes
StaffVariesSubmit a One-Time Purchase Request well in advance of the date supplies are needed to avoid later delays.
Admin3-5 business daysPlease allow at least 5 business days for processing.
BearBUY5-7 business daysRequests for additional documentation and/or corrections may delay procoessing.
Delivery of GoodsVariesFor questions regarding delivery/pick-up of requested items, contact the Admin Team.